Hebrew
|
English
About Us
Projects
Clients
Contact
Contact us
Please fill in the required fields and our representatives will get back to you as soon as possible.
Full name
Phone
Email
Message
Security code
X
Geology Geophysics
Gas and Oil Exploration
Hydrology, Surface Water Management and Drainage
Environmental
Remediation of Contaminated Sites
Environmental Management of Solid Waste Treatment and Landfill Facilities
Risk Assessments
Cleanup of contaminated soils and environmental support
Environmental Impact Assessments and Preparation of Environmental Documents
Groundwater pollution investigations
Water Supply
Water Hammer
Pipelines
Wells
Pumping Stations
General and Detail Design
Tunneling
Reservoir Design and Civil Engineering
Regulatory and Statutory Support
Hydrogeology
Tzofar Reservoir Pump Station
The water supply in the Moshav Tzofar area suffers from a shortage of suitable water storage facilities, so that during peak consumption, the wells that supply the water work continuously, and the hourly consumption is limited by the production capacity.
As part of the master plan for the middle Arava it was proposed to construct a reservoir and a pump station in the Tzofar area.
Ecolog designed the Tzofar reservoir for "Mekorot" company, including a pumping station on top of the reservoir Embankment.
The construction of the station was done in a few phases: during the first phase, two pumping units with an output of 600 m3/h x 60 meters (lift), and preparation for another 4 pumping units with the same output to be installed during a latter second phase.
The design includes hydraulic analysis for the integration of the reservoir and the pump station into the existing and planned water system, electromechanical design, civil engineering, water treatment, electricity and control systems.